Colton Sanitary Landfill Project
Client:
County of San Bernardino
Location:
Colton, CA
Description of Project:
The project included the installation of four million square feet of 50 mil LLDPE geomembrane and closure turf, import of 140,000 cubic yards of soil, placement of 30,000 tons of aggregate base, paving 200,000 square feet of asphalt, drilling and installation of 6,700 vertical feet of landfill gas well, and installation of 22,630 linear feet of landfill gas piping.