Description of Project:
Sukut preformed site civil work totaling 181 MWac, as well as 272 MW hours of battery storage. The scope consisted of site demolition, array and basin grading, access road construction, MV and DC trench and backfill, as well as the construction of BESS foundations with corresponding trenching.