Description of Project: 

The land where the storm drain project was located was being leased by a nursery. Existing irrigation pipes had to be kept in service at all times therefore daily coordination with the nursery operation was necessary to mitigate problems.
The following is a brief description of work completed:
• Construction of approximately 2,000 lineal feet of 120 foot diameter storm drain pipe,
• 1,300 lineal feet of double reinforced concrete box culvert,
• 5,000 lineal feet of sewer (15-35 feet depth), and associated road improvements including paving and v-ditch.

Client: 
The Irvine Community Development Company
Total Value: 
$16.20M
Date Completed: 
Wednesday, January 1, 2014
Location: 
Irvine, CA